Lost Horse Reservoir and Pipeline Project

5 Documents in Project

Summary

SCH Number
2009021073
Lead Agency
Planning and Research, Office of (Office of Planning and Research)
Document Title
Lost Horse Reservoir and Pipeline Project
Document Type
NOD - Notice of Determination
Received

Document Description
NOTE: Shortened Review/ Resubmittal IWA proposes to construct a steel water reservoir, with a five mg capacity, in the Indio Hills located just north of the City boundaries. The proposed reservoir would be 180 feet in diameter and 40 feet in height. It would be supported by a floor plate and surround by a 20-foot wide process-stone road. An 8-foot high ornamental/security fence would surround the entire pad and a 20-foot wide, 900 foot long service road would be constructed to connect the reservoir site to an existing dirt road that provides access to the site. A 24-inch-diameter inlet transmission pipeline and 18-inch diameter water outlet transmission pipeline constructed of cement mortar and lined steel pipe would connect the reservoir to an existing pump station located near the Golf Club area at the Terra Lago Golf Course.

Contact Information
Anders Wistrom
Indio Water Authority
83-101 Avenue 45
Indio, CA 92201

760-391-4046

Location

Coordinates
33°44'53"N 116°10'47"W
Cities
Indio
Counties
Riverside
Cross Streets
Dillon Road/Ave 44
Zip
92203
Total Acres
3.4
Parcel #
601150012-17 and 20
State Highways
I-10
Waterways
unnamed blue line stream approx 3700 feet to the east
Township
5
Range
8S
Section
8
Base
SBB&M

Notice of Determination

Approving Agency
Indio Water Authority/ City of Indio
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Indio Water Authority 83-101 Avenue 45 Indio, California 92201

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search