Landfill Parking Facility Project

2 Documents in Project

Summary

SCH Number
2009021037
Lead Agency
San Bernardino International Airport Authority
Document Title
Landfill Parking Facility Project
Document Type
NOD - Notice of Determination
Received
Posted
3/30/2009
Document Description
To maximize land use at the airport, the SBIAA has determined that use of the Former Air Force Base landfill as a parking area would be more effective use of the site. To accomplish this, SBIAA has prepared an Addendum to the Closure Plant/Post Closure and Maintenance Plan for the landfill to allow end use of the site as a parking facility. The Addendum has been reviewed and approved by state and federal agencies with jusridiction over the site closure. This project proposes an alternantive final cover that will alow use of the site as a parking area. The existing vegetationwill be removed and the upper soil layers affected will be sacrificed and re-compacted to meet parking area standards. About 4 inches of asphaltic concrete will be placed over the compacted subgrade in accordance with applicable standards for use as a parking facility and will be adequate to meet established requirements for final landfill cover.

Contact Information

Name
Mike Burrows
Agency Name
San Bernardino International Airport Authority
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
Cross Streets
Palm/Alabama and Third Street
Zip
92408
Total Acres
~20
State Highways
I10, I-210
Airports
San Bernardino International
Waterways
Santa Ana River
Township
1S
Range
3W
Section
8
Base
SBB&M

Notice of Determination

Approving Agency
SBIAA
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print