Vista Del Rio Residential Project

2 Documents in Project

Summary

SCH Number
2009011020
Lead Agency
City of Santa Ana
Document Title
Vista Del Rio Residential Project
Document Type
NOD - Notice of Determination
Received
Posted
8/10/2009
Present Land Use
Z: Open Space GP: Open Space
Document Description
The applicant proposes to alter the streambed of Loma Alta Creek to complete the remainder of the Loma Alta Creek El Camino Real Detention Basin. Construction of the Loma Alta Creek Detention Basin was previously authorized by CDFG along with another basin on Garrison Creek at El Camino Real (SAA #5-204-98). The detention basin at Garrison Creek was fully built, but only one-third of the basin at Loma Alta Creek was built prior to the expiration of the previous Agreement. Project activity to completely construction of the basin head and lateral masonry walls and finish the Loma Alta Creek Detention Basin includes the following: a) Trenching a 25-foot wide by 270-foot long construction corridor in order for the wall footings to be built and the walls anchored; b) Pile-driving the sheet pile wall sections into the ground; c) Minor grading and fill; and d) Construction of two concrete outfall structures within the lateral wall to drain the upper detention area into the lower detention area. (SAA #1660-2007-0329-R5).

Contact Information

Name
Melanie McCann
Agency Name
City of Santa Ana
Contact Types
Lead/Public Agency

Location

Cities
Santa Ana
Counties
Orange
Cross Streets
1600 West Memory Lane (also known as Garden Grove Blvd) at The City Drive South
Zip
92701
Total Acres
2.74
Parcel #
101-005-26
State Highways
HWY 22, I-5
Schools
Rio Contig, Riverdale
Waterways
Santa Ana River

Notice of Determination

Approving Agency
City of Santa Ana
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.