Browns Valley Irrigation District Dry Creek Recapture Project

4 Documents in Project

Summary

SCH Number
2008122105
Lead Agency
Browns Valley Irrigation District
Document Title
Browns Valley Irrigation District Dry Creek Recapture Project
Document Type
NOD - Notice of Determination
Received
Posted
12/14/2009
Document Description
BVID is proposing a tailwater recovery project that will relieve irrigation water supply constraints by pumping water from Dry Creek at times when Dry Creek flows are primarily composed of tailwater from irrigated lands draining to Little Dry Creek. The tailwater raises Dry Creek's temperature by 4-5 degrees Celsius and introduces sediment, nutrients, and other pollutants to the Creek approximately 1.8 miles upstream of its confluence with the Yuba River. By pumping from Dry Creek downstream of the confluence with Little Dry Creek, the project will remove some of the reclaimed water will be applied on rice lands where the elevated water temperature benefits rice will reduce the District's demand for water divided directly from the Yuba River, this balancing in diversion flows from the Yuba River. The Project proposes flow diversion of up to a maximum of 10 cfs from Dry Creek.

Contact Information

Name
Walter Catter
Agency Name
Browns Valley Irrigation District
Contact Types
Lead/Public Agency

Location

Counties
Yuba
Cross Streets
State Highway 20
State Highways
20
Waterways
Dry Creek, Yuba River
Township
16N
Range
5E
Base
MDM
Other Location Info
Browns Valley
Other Information
Section 21,22,28

Notice of Determination

Approving Agency
County of Yuba
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print