Vandenberg Air Force Base; Installation Restoration Program, Site 23-Landfill 5

2 Documents in Project

Summary

SCH Number
2008121129
Lead Agency
Department of Toxic Substances Control
Document Title
Vandenberg Air Force Base; Installation Restoration Program, Site 23-Landfill 5
Document Type
NOD - Notice of Determination
Received
Posted
3/12/2009
Document Description
The project is for the Department of Toxic Substances Control's (DTSC's) approval of a Focused Feasibility Study (FFS) plan to excavate and dispose of ~213 cubic yard of soil and sediment from 3 hot spot sub-areas of Site 23 (Landfill No. 5) at the Vandenberg Air Force Base (VAFB). This project will be performed in accordance with the FFS prepared for the U.S. Air Force by Tetra Tech, Inc., April 2008, which is incorporated by reference. The results of theRI, Ecological Risk Assessment (ERS) Addendum, and the Background Metal Sampling Technical Memorandum, which are incorporated by reference, identified chemicals of concern (COCs) present in the soil and sediment of Site 23. The COCs have demonstrated a risk to on-site workers due to exposure to polychlorinated biphenyls (PCBs) in soil at one sample location and significant risks to ecological receptors due to metals, pesticides, and PCBs in soil and sediment at the site.

Contact Information

Name
Manjulika Chakrabarti
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Counties
Santa Barbara
Cross Streets
13th Street and Iceland Avenue
Zip
93437
Total Acres
30
State Highways
No
Railways
No
Airports
VAFB Airfield
Schools
No
Waterways
Oak Canyon Drainage
Other Location Info
Vandenberg

Notice of Determination

Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.