Alta Oak Creek Mojave Wind Project, Alata Wind II, LLC; Alta Wind III, LLC; Alta Wind IV, LLC; and Alta Wind V, LLC (Streambed Alteration Agreement No. 1600-201

35 Documents in Project

Summary

SCH Number
2008121044
Lead Agency
Kern County
Document Title
Alta Oak Creek Mojave Wind Project, Alata Wind II, LLC; Alta Wind III, LLC; Alta Wind IV, LLC; and Alta Wind V, LLC (Streambed Alteration Agreement No. 1600-201
Document Type
NOD - Notice of Determination
Received

Document Description
The Project includes construction and operation of an 800 megawatt maximum wind energy generation facility. Major components of the project include up to 320 wind turbine generators, three or more electrical substations, meteorological towers, and one or two operations and concrete batch plants. Grading for the Project will excavate, contour, and place fill in a portion of several unnamed ephermal tributaries and Oak Creek. Project components that will occur in CDFG jurisdictional areas include new road construction, widening of existing stream crossings, and the trenching of underground electrical collection lines. Fill material will be placed into ~294 linear ft of CDFG jurisdictional ephermal drainage (~1.54 acres of permanent disturbance, and 2,751.5 cy of cut and 4,521.5 cy of fill). An additional 390 linear ft (~1.96 acres) will be temporarily disturbed during construction.

Contact Information
Craig Bailey
Department of Fish and Game
Central Region 1234 East Shaw Avenue
Fresno, CA 93710

559-243-4014 x 261

Location

Coordinates
35°03'09"N 118°21'22"W
Cities
Tehachapi Mojave
Counties
Kern
Cross Streets
Oak Creek Road and Tehachapi - Willow Springs Road
Zip
93501,560
Total Acres
~9,300
Parcel #
Multiple
Railways
SPRR
Airports
Mountain Valley
Waterways
Los Angeles River
Township
Multi
Range
Multi
Section
Multi
Base
SBB&M

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
Kern County Planning Dept 2700 M St, Suite 100 Bakersfield, CA 93301-2370

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
Yes