Crystal Springs Pipeline No.2 and Sherwood Point

5 Documents in Project

Summary

SCH Number
2008112050
Lead Agency
City and County of San Francisco
Document Title
Crystal Springs Pipeline No.2 and Sherwood Point
Document Type
NOD - Notice of Determination
Received
Posted
8/29/2011
Document Description
The Applicant has proposed to conduct maintenance in 19 locations along the CSPL2 alignment where pipeline rehabilitation, seismic retrofit of the pipe support piers, and general improvements are needed and some of the locations are within or adjacent to San Mateo Creek. The Sherwood Point Site is included in the SFPUC's Bioregional Habitat Mitigation Sites (BHMS) and has been proposed by the SFPUC to provide compensatory mitigation for impacts from CSPL 2 replacement work activities. The CA DFG is executing a Lake and Streambed Alteration Agreement Number 1600-2010-0203-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Husam Masri/San Francisco Public Utilities Commission.

Contact Information

Name
Greg Martinelli
Agency Name
DFG
Contact Types
Lead/Public Agency

Location

Cities
Brisbane, Brisbane, Daly City, Hillsborough, Millbrae, San Francisco, ..., Daly City, Hillsborough, Millbrae, San Francisco
Counties
San Francisco, San Mateo
Cross Streets
Various
Zip
various
Total Acres
~ 8
Parcel #
Various
State Highways
82, 101, I-280, I-380
Railways
CalTrain, BART
Airports
San Francisco Int'l
Schools
Various
Waterways
San Mateo Creek, San Francisco Bay

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.