Summary
- SCH Number
- 2008112050
- Lead Agency
- San Francisco, City and County of (City and County of San Francisco)
- Document Title
- Crystal Springs Pipeline No.2 and Sherwood Point
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 8/29/2011
- Document Description
- The Applicant has proposed to conduct maintenance in 19 locations along the CSPL2 alignment where pipeline rehabilitation, seismic retrofit of the pipe support piers, and general improvements are needed and some of the locations are within or adjacent to San Mateo Creek. The Sherwood Point Site is included in the SFPUC's Bioregional Habitat Mitigation Sites (BHMS) and has been proposed by the SFPUC to provide compensatory mitigation for impacts from CSPL 2 replacement work activities. The CA DFG is executing a Lake and Streambed Alteration Agreement Number 1600-2010-0203-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Husam Masri/San Francisco Public Utilities Commission.
- Contact Information
-
Greg Martinelli
DFG
Bay Delta Region 7329 Silverado Trail
Napa, CA 94558
Phone : (707) 944-5570
Location
- Cities
- Brisbane Brisbane, Daly City, Hillsborough, Millbrae, San Francisco, ... Daly City Hillsborough Millbrae San Francisco
- Counties
- San Francisco San Mateo
- Cross Streets
- Various
- Zip
- various
- Total Acres
- ~ 8
- Parcel #
- Various
- State Highways
- 82, 101, I-280, I-380
- Railways
- CalTrain, BART
- Airports
- San Francisco Int'l
- Schools
- Various
- Waterways
- San Mateo Creek, San Francisco Bay
Notice of Determination
- Approving Agency
- DFG
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- N/A
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- Yes
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.