Joshua Basin Water District Recharge Basin and Pipeline Project
5 Documents in Project
Summary
SCH Number
2008111082
Lead Agency
Joshua Basin Water District
Document Title
Joshua Basin Water District Recharge Basin and Pipeline Project
Document Type
EIR - Draft EIR
Received
Present Land Use
Z & GP: RL, RS, RM, RL, CS, GC, IN, FW
Document Description
JBWD proposes to construct one recharge basin facility that would be ~20 to 25 acres in size, and an extension of the Morongo Basin Pipeline from its existing terminus on Yucca Mesa Road to the new basin. Three alternative locations for the rechange basin are considered in the DEIR at an equal level of detail. The project would require a total of 29 acres for basin construction, which would include 22 wet acres; and would also involve construction of multiple (up to 6) 6 to 7 ft deep subbasins within the recharge basin. Subbasins would be seperated by overflow earthen weirs, allowing water to flow from subbasin to subbasin as needed. Control valves (housed within a small building on the site) would be used to add water to the subbasin, as necessary.
Water levels within the basins would not exceed original grade elevation and would be maintained at depths of three to five ft. Annual average recharge is anticipated to be ~2000 acre ft per year. However, with the availability of water being less than a full year, each site would be designed to allow the 2,000 acre ft per year recharge with a 50% water delivery scheduled. Therefore the recharge basins would be designed to accommodate a total capacity of up to ~4,000 acre ft fo half of the year to meet the goal of 2,000 acre ft per year of recharge. The earthen berms would visually screen the basin; an 8 ft chain-link fence would surround the site.
The proposed pipeline would include up to 24,000 linear ft of 16-24 inch diameter pipe connecting to the existing Morongo Pipeline at Yucca Mesa Road. The pipeline would be constructed within existing roadway rights-of-way.
Contact Information
Name
Tom Barnes
Agency Name
Joshua Basin Water District
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Bernardino
Cross Streets
Highway 62 at Joshua Tree
Zip
92252
Parcel #
060123115,060123114,060319141,060122129
State Highways
SR 62
Airports
No
Schools
Joshua Tree ES, Friendly Hills ES
Waterways
Joshua Creek, Yucca Creek
Township
1N
Range
6E
Other Location Info
City/Nearest Community: Joshua Tree
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Parks and Recreation, California Department of Transportation, District 8 (DOT), California Highway Patrol, California Native American Heritage Commission (NAHC), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), Department of Fish and Wildlife, Region 6, Department of Water Resources, Office of Historic Preservation, Resources Agency, Resources, Recycling and Recovery, State Water Resources Control Board, Division of Water Quality, Department of Toxic Substances Control
State Reviewing Agency Comments
Department of Toxic Substances Control
Development Types
Water Facilities (basin/pipeline)(Type Recharge)
Local Actions
Water infrastructure
Project Issues
Aesthetics, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Flood Plain/Flooding, Geology/Soils, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Noise, Public Services, Recreation, Solid Waste, Transportation, Vegetation, Wetland/Riparian
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.