Interstate-5 North Stockton Corridor Improvements Project

7 Documents in Project

Summary

SCH Number
2008102101
Lead Agency
Caltrans 10 (Stockton) (California Department of Transportation, District 10)
Document Title
Interstate-5 North Stockton Corridor Improvements Project
Document Type
NOD - Notice of Determination
Received

Document Description
Caltrans proposes to widen three bridges in their medians over Calaveras River, Fourteen Mile Slough, and Five Mile Slough along 7.4 miles of I-5 in San Joaquin County. The construction is scheduled for summer of 2011 and in-water work will last 1 season. At the Calaveras River and Fourteen Mile Slough locations 49 24 inch cast-in-drill-hole (CIDH) piles will be installed. To install the CIDH piles temporary casings. The soil will be removed and disposed of offsite. Water and slurry material will be pumped to baker tanks. Temporary trestle bridges supported on CIDH piles will be installed for access, they will be removed or cut below grade after construction. No water diversion or coffer dam will be necessary. At Five Mile Slough a 5 ft length of existing box culvert will be removed and replaced, as will the existing head walls. Coffer dams and a stream diversion will be necessary to complete this work. The Permittee shall submit a coffer dam and diversion plan to the Department for approval prior to installation. No trees will be removed to build this project.

Contact Information
Melissa Escaron
California Department of Fish and Game
Bay Delta Region P.O. Box 47
Yountville, CA 94599

707-339-0334

Location

Cities
Stockton
Counties
San Joaquin
Cross Streets
From 0.2 miles south of Charter Way/Martin Luther King Jr. Blvd to 1.8 miles north of 8 Mile Rd
Zip
95677
State Highways
Interstate 5, SR 99, SR4
Schools
Bear Creek High School
Waterways
Smith Canal, Bear Creek, Calaveras River, and 14 mile, 5 mile & Mosher Slough

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
Caltrans 2015 East Shields, Suite 100 Fresno, CA 93726

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search