Tulelake Wastewater Upgrade Project

4 Documents in Project

Summary

SCH Number
2008102070
Lead Agency
City of Tulelake
Document Title
Tulelake Wastewater Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
1/6/2011
Present Land Use
wastewater treatment plant and agricultural lands
Document Description
Tulelake is currently under the terms of a Cease and Desist Order R1-2004 -0074 is issued by the North Coast Regional Water Quality Control Board (Region 1). Under the terms of the Order, Tulelake is required to develop an alternative to discharging treated effluent into TID Drain 44-B1. The proposed improvement include refurbishment of the existing treatment facility, the purchase and construction of an unlined constructed wetland effluent disposal site, and conversion of the non-operational effluent filters to treatment wetlands. The treatment wetlands would have an impermeable liner and water would be evaporated and transpired. The State Water Resources Control Board is processing a wastewater change petition to change the point of discharge of treated wastewater, purpose of use, place of use and quantity of discharge to implement the new project.

Contact Information

Name
Jim Cook
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Tulelake
Counties
Siskiyou
Cross Streets
Dean Calias Way and Ray Dehlerich Way
Zip
96134
Total Acres
30
State Highways
139
Railways
Modco Northern
Schools
Tulelake USD
Waterways
Tulelake Irrigation drainage Canal #44-B-1; Lost River
Township
48N
Range
4E
Section
35
Base
Mt. Diab

Notice of Determination

Approving Agency
State Water Resources Control Board, Division of Water Rights
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print