Intermountain Conservation Camp Replacement Project

3 Documents in Project

Summary

SCH Number
2008102002
Lead Agency
California Department of Forestry and Fire Protection (CAL FIRE)
Document Title
Intermountain Conservation Camp Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
12/3/2008
Present Land Use
Existing facility/General Agriculture "A-1"/Intensive Agriculture
Document Description
The purpose of the project is to allow the ICC to more efficiently operate at its current capacity, primarily by replacing and expanding the current infrastructure and service facilities. The ICC is currently an 80-bed facility; project implementation will increase inmate capacity to 88 beds. This is considered to be an insignificant increase with regard to environmental impacts. The project will include construction of a new ~10,938 square foot barracks, with the addition of two shower/restroom areas; construction of a new ~5,000 square foot kitchen/mess hall building; a new ~4,250 square foot dayroom building; a ~3,960 square foot garage, a ~4,240 square foot vehilce maintenance facility; an ~880 square foot addition to the CalFire administration building; and a ~750 square foot addition to the CDCR administration building; construction of ~700 linear feet of sewer line; ~500 linear feet of water line; and the installation of electrical, telepjone, and gas lines to new buildings. The project will include the paving of the existing dirt access road; replacement of some existing tarmac; the addition of some pavement and vehicle aprons; and the construction of new walkways within the ICC. The project will include the removal of approximately two dozen pine and oak trees.

Contact Information

Name
Dan Foster
Agency Name
California Department fo Forestry and Fire Protection
Contact Types
Lead/Public Agency

Location

Counties
Lassen
Cross Streets
Foothill Road
Zip
96009
Parcel #
001-100-22
State Highways
None
Railways
None
Airports
None
Schools
NOne
Waterways
Cedar Run Creek
Township
38N
Range
6E
Section
24
Base
MDB&M
Other Location Info
Bieber

Notice of Determination

Approving Agency
California Department of Forestry and Fire Protection
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.