Senior Canyon Mutual Water Company Pipeline Project

3 Documents in Project

Summary

SCH Number
2008101120
Lead Agency
California Department of Public Health (CDPH)
Document Title
Senior Canyon Mutual Water Company Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
10/21/2010
Document Description
The Senior Canyon Mutual Water Company is proposing to install approximately 1500 linear feet of a new water pipe, including two suspended spans of approximately 130 feet over a dry ravine and approximately 250 feet over Senior Canyon Creek. The creek crossing would replace two pipelines and consist of a pipe bridge with three pipes installed and secured. The project would also include the installation of instrumentation, construction of a 160sf utility structure for storage of materials and tools, and new security fencing around the existing filters. Approximately 680 linear feet of roadway leading to the filters and instrumentation would be widened and paved to meet Ventura County Fire Department requirements for adequate emergency vehicle access. A dilapidated shed currently used for storage would be removed and replaced by the proposed 160sf utility structure.

Contact Information

Name
Ron Merckling
Agency Name
Casitas Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Ojai
Counties
Ventura
Cross Streets
Highway 150, Senior Canyon Creek and Ladera Road
Total Acres
5.5
Parcel #
140-120-02, 03, 07, 08, 09, 070-029
Township
5N
Range
22W
Section
32

Notice of Determination

Approving Agency
Casitas Municipal Water District
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print