Recycled Water Resevoirs R-41, R-42, and R-43

4 Documents in Project

Summary

SCH Number
2008101094
Lead Agency
City of Chino Hills
Document Title
Recycled Water Resevoirs R-41, R-42, and R-43
Document Type
NOD - Notice of Determination
Received
Posted
12/15/2008
Present Land Use
Open Space/Rural Residential
Document Description
The proposed project will construct three steel recycled water reservoirs. R-41 is proposed as a 0.5 MG reservoir adjacent to existing R-11 (domestic water). Work would include installation of approx. 500 lineal ft. of 8 in. recycled water pipeline and approx. 2,000 if of paved access road as well as related appurtenances. R-42 is proposed as a 2.0 MG reservoir adjacent to existing R-4 and R-17 (domestic water). Work would include installation of approx. 500 lineal ft. of 16 in. recycled water pipeline and related appurtenances. R-43 is proposed as a 2.0 MG reservoir on an already graded pad. Work would include installation of approx. 16 in. recycled water pipeline to connect to the existing recycled water system and related appurtenances.

Contact Information

Name
Anne R. Dutrey
Agency Name
City of Chino Hills
Contact Types
Lead/Public Agency

Location

Cities
Chino Hills
Counties
San Bernardino
Zip
91709
Total Acres
~10
State Highways
142 Carbon Canyon Road
Township
8W
Range
2S
Base
SBM

Notice of Determination

Approving Agency
City of Chino Hills
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print