2008 Water System Engineer's Report

5 Documents in Project

Summary

SCH Number
2008092095
Lead Agency
City of Modesto
Document Title
2008 Water System Engineer's Report
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2010
Document Description
The Engineer's Report identifies a Capital Improvement Program (CIP), for system-side implementation needed to deliver safe and reliable water, which will effectively meet water demand requirements under both existing and future developed conditions. The Programs, as analyzed through this environmental review process, is the collection of CIP projects and programs proposed in the Engineer's Report. Specifically, the following 3 primary improvement types, based on improvement frequency, are identified in the Engineer's Report as being needed to meet: Major Project Improvements - These projects will occur once and are associated with large joint ventures with other agencies or cities (e.g., City-Side Downstream Improvements related to the Regional Surface Water Supply Project (RSWSP)). Project Improvements: These projects will occur once or very infrequently (e.g., construction of a Corporation Yard). Program Improvements: These program related projects will occur more periodically and over time (e.g., updating the Water Master Plan). Most Major Project, Project, and Program Improvements proposed in the Engineer's Report primarily relate to storage tanks, groundwater wells, and pipelines, but also include recommendations for future planning efforts, such as updates to the City's groundwater, urban water, or water supply management plans.

Contact Information

Name
Jack Bond
Agency Name
City of Modesto Utility Projects and Planning Department
Contact Types
Lead/Public Agency

Location

Cities
Modesto
Counties
Stanislaus
State Highways
99, 108
Airports
Modesto City/County
Waterways
Tuolumne and Stanislaus River

Notice of Determination

Approving Agency
City of Modesto
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print