Folsom Plan Specific Area Plan Project, Master SAA 1600-2012-0198-R2

38 Documents in Project

Summary

SCH Number
2008092051
Lead Agency
City of Folsom
Document Title
Folsom Plan Specific Area Plan Project, Master SAA 1600-2012-0198-R2
Document Type
NOD - Notice of Determination
Received
Posted
2/18/2014
Present Land Use
PLU: AG-80 (also AR-10, AG-20, SPA, RCA)
Document Description
The California Department of Fish and Game is executing Streambed Alteration Agreement number 1600-2012-0198-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, the Folsom South Area Group. The project is to allow the Folsom South Area Group and its employees, agents, or contractors and their subcontractors to conduct the authorized associated with the Backbone Infrastructure Project within the Folsom Specific Plan Area (SPA). The Backbone Infrastructure Plan includes major roads and trails, water and sewer infrastructure, and storm drain infrastructures within the SPA.

Contact Information

Name
David Miller
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Folsom
Counties
Sacramento
Cross Streets
U.S. Highway 50, Prairie City Road, White Rock Road, Empire Ranch Rd.
Zip
95630
Total Acres
3,584
State Highways
US 50
Railways
RT, Union Pacific
Schools
Folsom HS, others
Waterways
Alder Creek, American River, Coyote Creek, Deer Creek

Notice of Determination

Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print