Devil Canyon Well No. 8 Project
2 Documents in Project
Summary
SCH Number
2008091115
Lead Agency
San Bernardino Valley Municipal Water District
Document Title
Devil Canyon Well No. 8 Project
Document Type
NOD - Notice of Determination
Received
Posted
11/24/2008
Document Description
The objective of the proposed well, Devil Canyon Well No. 8, is to continue to increase the SBMWD's water production capacity to meet peak day demand requirements of existing development and future connections. The SBMWD's proposes to construct the new well and related appurtenances within the City of San Bernardino. The new well is anticipated to be drilled to a depth of ~400ft. below ground surface (bgs). The well is anticipated to yield ~2,000gal./min. (gpm). Water pumped from the proposed well will be treated with chlorine gas at the well site to provide disinfection. The drilling and development of the proposed well will take ~3 to 4 weeks. The well site is proposed to be equipped with a submersible pump and matched control panel. The pump motor will be installed above ground. The well site will consist of a 20in. well casing, cement grout and gravel pack, a screened air vent, and a 2in. sounding tube. A well housing will enclose the permanent facilities. In addition, the project includes the installation of a chlorinator building for onsite disinfection, a Southern California Edison vault, a block wall to surround the proposed facilities and security gates.
Contact Information
Name
Matthew Litchfield
Agency Name
San Bernardino Municipal Water District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
San Bernardino
Counties
San Bernardino
Cross Streets
Campus Parkway and Valles Dr.
Total Acres
2
State Highways
I-215
Railways
BNSF Railway East/West Mail
Airports
Southern California Logistics
Township
1N
Range
4W
Base
SBM
Notice of Determination
Approving Agency
San Bernardino Municipal Water Department
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.