Agreement between the Department of Water Resurces of the State of California and Antelope Valley-East kern Water Agency for Construction, Operation, and Mainte

6 Documents in Project

Summary

SCH Number
2008091061
Lead Agency
Palmdale, City of (City of Palmdale)
Document Title
Agreement between the Department of Water Resurces of the State of California and Antelope Valley-East kern Water Agency for Construction, Operation, and Mainte
Document Type
NOD - Notice of Determination
Received

Document Description
The UAC Turnout will consist of two 48-inch diameter steel discharge pipes that manifold into one 48-inch diameter steel discharge pipe, a new reinforced concrete metering vault structures that houses a 48-inch magnetic flowmeter, a control building, safety devices, flow recorder and oher related appurtenances. The flow recorder will be located within an instrument cabinet installed as part of this work and be connected to DWR's Supervisory Control and Data Acquisition System. The maximum design capacity of the UAC Turnout will be 100 cubic feet per second to provide a maximum monthly delivery of 3,000 acre-feet. The UAC Turnout provides the water source for the UAC Recharge project.

Contact Information
Brian Heiland
DWR
1416 9th Street, Rm 1620
Sacramento, CA 95814

916-653-4547

Location

Coordinates
34°35'5"N 118°10'25"W
Cities
Palmdale
Counties
Los Angeles
Cross Streets
25th Street West and Elizabeth Lake Road
Zip
93551
Total Acres
87
Parcel #
3003-030-018,3003-084-904,3003-
State Highways
14
Railways
No
Airports
No
Schools
Highland High
Waterways
Amargosa Creek and California Aqueduct
Township
6N
Range
12W
Section
29
Base
SBB&M

Notice of Determination

Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes