Applegate Wastewater Treatment Plant Closure & Pipeline Project

7 Documents in Project

Summary

SCH Number
2008082116
Lead Agency
Placer County
Document Title
Applegate Wastewater Treatment Plant Closure & Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
3/20/2012
Present Land Use
Existing Wastewater Treatment Plant/RA-B-100/Rural Estate 2.3-4.6 acre min.
Document Description
The California Department of Fish and Game is executing Lake or Streambed Alteration Agreement number 1600-2011-0174-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, Placer County Department of Facility Services. The project is limited to construction of a pumping station and placement of a force-main sewer pipeline to connect the former Applegate Waste Water Treatment Plant to the SMD1 waste water collection system in North Auburn. The project will require 19 hand dug trenches under existing drainage culverts for placement of sewer pipe, and fill of a portion of an intermittent drainage and associated wetlands with temporary impacts to the associated riparian area (temporary impacts to approx 0.066 of willows with permanent impacts to approx. 0.011 acres of willows) for construction of the staging area at the site of the initial pump station on Applegate Road near Interstate Highway 80.

Contact Information

Name
Garry Kelley
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Counties
Placer
Zip
95703
Total Acres
84.9
Parcel #
Multiple
State Highways
I-80
Railways
Union Pacific
Township
13
Range
9E
Section
8
Base
MDB&M
Other Location Info
City/Nearest Community: Applegate
Other Information
Nearest City: Applegate

Notice of Determination

Approving Agency
Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print