Napa River Rutherford Reach Restoration Project

8 Documents in Project

Summary

SCH Number
2008082086
Lead Agency
Napa County
Document Title
Napa River Rutherford Reach Restoration Project
Document Type
NOD - Notice of Determination
Received
Posted
6/28/2012
Document Description
The Reach 8 project is component of the larger Napa River Rutherford Reach Restoration Project which is intended to enhance or restore aquatic and riparian habitats along 4.5 miles of the Napa River between Zinfandel Lane and the Oakville Cross Road. Reach 8 of the project extends approximately 4,085 feet along the river, between the Rutherford River, crossings to the north and the Oakville Road crossing to the south. This portion of the Project includes inset floodplain benching, sediment removal, bank stabilization, invasive species control, and placement of in-channel grade control and habitat enhancement structures. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number 1600-2012-0074-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Richard Thomasser, Napa County Department of Public Works.

Contact Information

Name
Suzanne Gilmore
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Napa
Counties
Napa
Cross Streets
Oakville Cross Road and Zinfandel Lane
Zip
94559
State Highways
128 and 29
Railways
Napa Valley Wine Train
Waterways
Napa River

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print