Authorization to Issue Bonds to Finance Public Facilities for McKinley Village (P09-086)

6 Documents in Project

Summary

SCH Number
2008082049
Lead Agency
City of Sacramento
Document Title
Authorization to Issue Bonds to Finance Public Facilities for McKinley Village (P09-086)
Document Type
NOD - Notice of Determination
Received
Posted
5/5/2016
Present Land Use
various
Document Description
On April 29, 2014, the City of Sacramento adopted Resolution No. 2014-0102 (certifying the EIR for the McKinley Village Project and adopting the Mitigation Monitoring Program and CEQA Findings of Fact and Resolution No. 2014-0106. Through a special, mailed ballot election held on July 28, 2015, qualified electors in Community Facilities District No. 2015-04 authorized the issuance of $10 million principal amount of special-tax bonds under the Mello-Roos Community Facilities Act of 1982. This NOD addresses only the City's subsequent action on May 3, 2016 to adopt Resolution No. 2016-0133, which authorizes the issuance of up to $8 million principal amount of special-tax bonds (Series 2016 Bonds) to finance the acquisition and construction of certain public facilities associated with the previously approved McKinley Village Project.

Contact Information

Name
Dana Allen
Agency Name
City of Sacramento Community Development Dept.
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
A Street, Lanatt St, Alhambra Blvd, Bus 80
Zip
95819
Total Acres
48.75
Parcel #
various
State Highways
Bus 80
Railways
UPRR
Schools
Theodore Judah
Waterways
American River

Notice of Determination

Approving Agency
City of Sacramento
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes