Iron Canyon Fish Ladder Rehabilitation

6 Documents in Project

Summary

SCH Number
2008082017
Lead Agency
City of Chico
Document Title
Iron Canyon Fish Ladder Rehabilitation
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2009
Document Description
Repair and expansion of the Iron Canyon Fish Ladder in Bidwell Park. Project work includes: 1) clearing and preparation of a staging area on the top of the bluff; 2) scaling of the canyon wall to remove any statically or seismically unstable rock which could fall and injure workers in the creek; 3) installation of an emergency egress system including attachment of an elevator type system to the canyon wall and construction of a bridge from the canyon rim to the top of the egress system; 4) installation of at least one equipment platform in the canyon to support compressors and other equipment; 5) physical removal of boulders through the use of jackhammers, crowbars and possibly other mechanical equipment; 5) physical removal or repair of damaged weirs and pools in the fishway; 7) construction of additional pools and weirs to improve the fish ladder; 8) installation of additional fish passage slots; 9) demobilization and removal of all construction equipment and subsequent Revegetation of impacted areas within the project.

Contact Information

Name
Robert C. hosea
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Chico
Counties
Butte
Cross Streets
Upper Park Road
Zip
95928
Total Acres
1.2
Parcel #
016-240-002; 063-290-016
State Highways
32
Waterways
Big Chico Creek
Township
22N
Range
2E
Section
Unsect

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print