Recycled Water Expansion Project: Napa MST Culvert Crossings

33 Documents in Project

Summary

SCH Number
2008072096
Lead Agency
Sonoma County Water Agency
Document Title
Recycled Water Expansion Project: Napa MST Culvert Crossings
Document Type
NOD - Notice of Determination
Received
Posted
9/18/2013
Present Land Use
Napa State Hospital portable office building/Public Institutional use
Document Description
Open cut trenching at nine different stream crossing locations to install a new recycled water pipeline within existing paved roadways. The existing culverts under the roadways along the pipeline alignment will interfere with the new pipeline installation. Therefore, the existing culverts will be excavated and exposed, and then 4-foot section of culvert (within the trench excavation limits) will be cut and removed. Trenching will continue vertically below the removed culvert, until a sufficient depth is reached to install the recycled water pipeline below the path of the culvert.

Contact Information

Name
Suzanne Gilmore
Agency Name
CA Dept. of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Napa, Novato, Sonoma
Counties
Marin, Napa, Sonoma
Cross Streets
Imola Avenue, Harding Street, Coombsville Road, 2nd Avenue
Zip
94559
Total Acres
5.91
Parcel #
various
State Highways
Hwy 221, 121
Schools
Silverado Jr HS
Waterways
North San Pablo Bay, Lake Camille, Napa River, Tulocay Creek
Township
5N
Range
4W
Section
12

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print