Recycled Water Expansion Project: Napa MST Culvert Crossings
33 Documents in Project
Summary
SCH Number
2008072096
Lead Agency
Sonoma County Water Agency
Document Title
Recycled Water Expansion Project: Napa MST Culvert Crossings
Document Type
NOD - Notice of Determination
Received
Posted
9/18/2013
Present Land Use
Napa State Hospital portable office building/Public Institutional use
Document Description
Open cut trenching at nine different stream crossing locations to install a new recycled water pipeline within existing paved roadways. The existing culverts under the roadways along the pipeline alignment will interfere with the new pipeline installation. Therefore, the existing culverts will be excavated and exposed, and then 4-foot section of culvert (within the trench excavation limits) will be cut and removed. Trenching will continue vertically below the removed culvert, until a sufficient depth is reached to install the recycled water pipeline below the path of the culvert.
Contact Information
Name
Suzanne Gilmore
Agency Name
CA Dept. of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Location
Cities
Napa, Novato, Sonoma
Counties
Marin, Napa, Sonoma
Cross Streets
Imola Avenue, Harding Street, Coombsville Road, 2nd Avenue
Zip
94559
Total Acres
5.91
Parcel #
various
State Highways
Hwy 221, 121
Schools
Silverado Jr HS
Waterways
North San Pablo Bay, Lake Camille, Napa River, Tulocay Creek
Township
5N
Range
4W
Section
12
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes