MST Recycled Water Project - Imola Avenue Segment
33 Documents in Project
Summary
SCH Number
2008072096
Lead Agency
Sonoma County Water Agency
Document Title
MST Recycled Water Project - Imola Avenue Segment
Document Type
NOD - Notice of Determination
Received
Posted
8/24/2011
Present Land Use
Residential/Agricultural/Commercial
Document Description
New construction of two 24 inch piers to support a 24-inch diameter steel pipe, removal and replacement of rock slope protection, removal of Himalayan blackberry, and planting of native vegetation. The project is located on Cayetano creek adjacent to 2022 Imola Avenue in the City of Napa, California. The California Department of Fish and Game is executing a Lake or Streambed Alteration Agreement Number 1600-2011-0122-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Andrew Damron/Napa Sanitation District.
Contact Information
Name
Suzanne Gilmore
Agency Name
DFG, Bay Delta Region
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Napa, Novato, Sonoma
Counties
Marin, Napa, Sonoma
Cross Streets
Bolling Circle, Main Gate Road, Hamilton Parkway, Hangar Avenue, various side streets
Zip
94954
Total Acres
16
Parcel #
155-011-15; 155-011-33; 155-011-24; 155-011-19
State Highways
Hwy 101
Railways
Norwest Pacific
Schools
Hamilton ES
Waterways
Pacheco Creek, Miller Creek, North San Pablo Bay
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.