Natomas Levee Improvement Program (NLIP) Landside Improvements Project-Phase 3 Project
20 Documents in Project
Summary
SCH Number
2008072060
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Natomas Levee Improvement Program (NLIP) Landside Improvements Project-Phase 3 Project
Document Type
NOD - Notice of Determination
Received
Posted
3/26/2010
Document Description
SAA# 1600-2010-0009-R2
Modification of Elkhorn Pumping Plant - Under the Phase 3 Elkhorn Pumping Plant Project, the discharge pipes for the Natomas Central Mutual Water Company (NCMWC) pumping plant are required to cross the Sacramento River east levee above the new "200-year" design flood elevation. To accommodate this, the existign discharge pipes and the existing pumps for the Elkhorn Pumping Plant would need to be replaced to allow continued performance after the levee improvements and pipe-raising/repalcement is finished.
Contact Information
Name
Gary L. Hobgood
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Sacramento
Counties
Sacramento, Sutter
Cross Streets
Various
State Highways
5, 99, 80
Airports
Sacramento International
Waterways
Sac & American R., Natomas Cross Can., Natomas East Main Drainage Can., Pleasant Grove Cr. Can.
Notice of Determination
Approving Agency
Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.