Interstate 80 Bicycle/Pedestrian Bridge Project (HC21/K150020000)

3 Documents in Project

Summary

SCH Number
2008072005
Lead Agency
City of Sacramento
Document Title
Interstate 80 Bicycle/Pedestrian Bridge Project (HC21/K150020000)
Document Type
NOD - Notice of Determination
Received
Posted
2/1/2010
Document Description
The City of Sacramento proposed to construct a pedestrian/bicycle overcrossing (POC) over Interstate 80 adjacent to the Natomas Main Drainage Canal where the Natomas West and Natomas East Drainage canals merge. The City also proposes to construct an at-grade level bridge (Canal Bridge) across the West Drainage Canal to link the north end of the POC with the existing trail. The project will also consist of all railings and fencing, grading, paving and slope protection, signage, and lighting associated with the POC. The POC will consist of a cast-in-place box girder section, supported by two east-in-place concrete abutments and five cast-in-place concrete columns on driven piles. The Canal Bridge will include a pre-manufactured steel truss "flat slab" structure this unit will consist of weathering steel, concrete deck, and smooth steel handrails; it will be designed to be removable as needed by the Reclamation District 1000 for maintenance of the Canal. Concrete will also line the canal bottom under the bridge and 10 feet beyond in both directions.

Contact Information

Name
Gary L. Hobgood
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
Interstate 80 and Interstate 5 (I-80 Post Mile 2.10 approximately 1/3 mile west of I-5)
Zip
95833
Total Acres
2.0 +/-
Parcel #
parts of 225-0022-070, -078, -079, -092, -097, -099
State Highways
I-80, I-5
Waterways
Natomas West, East, and Main Drainage Canals, Sacramento River

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.