General Plan and Zoning Code Update

7 Documents in Project

Summary

SCH Number
2008071012
Lead Agency
City of El Monte
Document Title
General Plan and Zoning Code Update
Document Type
NOD - Notice of Determination
Received
Posted
1/15/2014
Present Land Use
Various
Document Description
The Project is implementation of a Removal Action Workplan (RAW) for the construction of a cap for the mitigation of lead-impacted soil and completion of a removal action of undocumented fill beneath portions of the proposed development associated with the presence of a former "burn dump" at 3527 Santa Anita Avenue, El Monte, California (site). The draft RAW recommend installation, operation, and maintenance of a Geosynthetic Clay Layer (GCL), to be installed at the ground surface as a means to prevent direct contact with the lead impacted soil. Furthermore, an Operations and Maintenance plan will be developed to ensure the integrity of the cap in perpetuity. Finally, the land owner will record a Land Use Covenant, ensure future land use consistent with the proposed development and DTSC is to be notified of any changes to future land use.

Contact Information

Name
Riachard D. Allen
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
El Monte
Counties
Los Angeles
Regions
Citywide
Cross Streets
Citywide
Zip
91731
State Highways
I-10, I-605
Airports
El Monte Airport
Waterways
Rio Hondo River, San Gabriel River

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print