Bidwell Canyon Stage 3 Boat Ramp Extension Project (Lake Alteration Agreement No. 1600-2015-0169-R2)
5 Documents in Project
Summary
SCH Number
2008062085
Lead Agency
California Department of Water Resources
(DWR)
Document Title
Bidwell Canyon Stage 3 Boat Ramp Extension Project (Lake Alteration Agreement No. 1600-2015-0169-R2)
Document Type
NOD - Notice of Determination
Received
Posted
9/10/2015
Present Land Use
Within Lake Oroville, part of State Recreation Area
Document Description
The California Department of Fish and Game is executing Lake or Streambed Alteration Agreement number 1600-2015-0169-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, California Department of Water Resources as represented by Eric See.
DWR proposes to extend the existing Bidwell Canyon Boat Ramp from elevation 675 to 640 ft above mean sea level (msl). The proposed extension is a 235-ft long by 53 ft wide concrete ramp, consisting of three 15-ft wide launching lanes and an 8-ft wide lane to accommodate a boarding float. Grading and placement of compacted fill and aggregate road base will precede concrete placement. The structure will be protected from erosion by geotextile fabric and rock slope protection. In-water work may occur up to a five foot depth.
Contact Information
Name
Kursten Sheridan
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Oroville
Counties
Butte
Cross Streets
Bidwell Canyon Road, Arroyo Drive, Kelly Ridge Road, Hwy 162
Zip
95966
Total Acres
4.7
State Highways
Hwy 162
Waterways
Feather River / Lake Oroville
Township
20N
Range
5E
Section
31
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No