Document Description
The project would add a sixth floor to Porter College House B, an existing 73,500-gross-square-foot (gsf) student residence hall on the western edge of the central UCSC campus. The existing roof and fifth floor walls will be demolished to the floor slab, the fifth floor walls will be reconstructed and an additional sixth floor and roof will be built. The project will add 18,715 gsf to the existing building and would accommodate 120 new student beds. The project will increase the height of the building from 54 feet to 74 feet. Project construction will take place in conjunction with seismic corrections and capital renewal work at Porter College House B and Porter College Dining Common (a total of 101,802 gsf) previously authorized as the Porter College Seismic and Capital Renewal Phase 1 Project.

Contact Information

Name
Charlotte Strem
Agency Name
University of California
Contact Types
Lead/Public Agency

Location

Cities
Santa Cruz
Counties
Santa Cruz
Cross Streets
Heller Drive and Meyer Drive
Zip
95064
Total Acres
0.25
Parcel #
01-011-13
State Highways
1
Schools
Westlake Elementary
Waterways
San Lorenzo River
Township
11S
Range
2W
Base
MDB&M

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.