Remedial Action Plan, Proposed Central Region Elementary School #20, Site 11

6 Documents in Project

Summary

SCH Number
2008051093
Lead Agency
Department of Toxic Substances Control
Document Title
Remedial Action Plan, Proposed Central Region Elementary School #20, Site 11
Document Type
NOD - Notice of Determination
Received
Posted
12/2/2009
Document Description
The project involves approval of a Remedial Action Plan (RAP) by DTSC for the Central Region Elementary School #20, Site 11 pursuant to Health and Safety Code chapter 68. The RAP focuses on 1) approximately 49,000 tons of contaminated soil that will be removed and taken off-site for disposal. It will take ~2,130 truckloads to remove the contaminated soil from the site; and (2) installation and operation of gas mitigation system and enhanced bioremediation of the groundwater. The Site is impacted by Total Petroleum Hydrocarbons (TPHs), Volatile Organic Compounds (VOCs), metals, methane and hydrogen sulfide. After completion of the planned excavations, cleanup confirmation sampling and Site restoration will be conducted. If necessary, additional soil volume will be excavated to ensure all onsite impacted soils containing the identified chemical of concerns (COCs) at concentrations of the corresponding cleanup levels or above have been properly removed.

Contact Information

Name
Amit Pathak
Agency Name
California Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles
Counties
Los Angeles
Cross Streets
108 South Bimini Place and 3600 West Council Street
Zip
90004
Total Acres
8.13
Parcel #
5501-010-008; -008-908
State Highways
101
Schools
Virgil Middle School
Township
1S
Range
13W
Section
19
Base
SBB&M

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.