Blackie Road Safety Improvements
8 Documents in Project
Summary
SCH Number
2008051009
Lead Agency
Monterey County
Document Title
Blackie Road Safety Improvements
Document Type
NOD - Notice of Determination
Received
Posted
6/14/2010
Document Description
Combined Development Permit consisting of: 1) a Coastal Development Permit and Use Permit for the construction of approximately 65,531sf of paved shoulders and drainage improvements to Blackie Road within the existing right-of-way, including curve warning signage, center line rumble-strips, re-striping, and approximately 300 linear feet of retaining walls; 2) a Coastal Development Permit to allow the removal of 47 trees (44 oak and 3 eucalyptus, including 5 landmark oak and 1 landmark eucalyptus); 3) a Coastal Development Permit to allow development on slope greater than 25 percent; 4) a Use Permit to allow development on slope greater than 30 percent; and grading consisting of approximately 7,219 cubic yards of cut and 2,177 cubic yards of fill (net export of approximately 5,042 cubic yards). The project also includes the removal of 20 trees (11 oak and 9 eucalyptus, including 5 landmark oak) in the Inland area, which is exempt from permit requirements under Monterey County Code 21.64.260.F.2.
Contact Information
Name
Joseph Sidor
Agency Name
Monterey County Resource Mgmt. Agency Public Works Dept
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Monterey
Cross Streets
U.S. Highway 101 and Merritt Street
Zip
93907
Total Acres
16.8
State Highways
U.S. 101
Railways
No
Airports
No
Schools
No
Waterways
Merritt Lake
Other Location Info
City/Nearest Community: Prunedale
Notice of Determination
Approving Agency
Planning Commission County of Monterey
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A