Vineyard Creek Improvement Project

2 Documents in Project

Summary

SCH Number
2008042016
Lead Agency
Marin County
Document Title
Vineyard Creek Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/28/2008
Present Land Use
SF-5 (Single-Family Residential 2-4 units per 1 acre); R-1:B2 (Single-Family Residential 2-4 units per 1 acre)
Document Description
The Vineyard Creek Channel Enhancement Project will be undertaken to meet the following objectives: improve fish passage and habitat restoration, increase and maintain flood conveyance, stabilize incised and eroding banks; improve water quality; and promote an ecologically healthy riparian corridor. The project will improve flood conveyance and fish habitat and passage within the project reach. Creek corridor modifications will include replacing the culverts at the Center Road crossing with a free span bridge or bottomless arch culvert, providing modifications to the bed and bank to eliminate erosion risks to adjacent properties and improve water quality, promoting active channel conveyance of both water and sediment and providing improved low- and high-flow fish passage, improved water flow channel from and enhanced in-stream habitat. The riparian corridor will be replanted to provide a low density native under-story, "soft" bank erosion protection (where possible) and increased canopy.

Contact Information

Name
Tim Hampton
Agency Name
Marin County Department of Public Works
Contact Types
Lead/Public Agency

Location

Cities
Novato
Counties
Marin
Cross Streets
Center Road and Wilmac Road
Zip
94947
State Highways
101

Notice of Determination

Approving Agency
Department of Public Works Principal Civil Engineer
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print