Via Real Main Sewer Line Relocation Project (Lake or Streambed Alteration Agreeemnt No. 1600-2015-0082-R5). This project is part of a larger project titled: "Li

7 Documents in Project

Summary

SCH Number
2008041158
Lead Agency
California Department of Transportation, District 5
Document Title
Via Real Main Sewer Line Relocation Project (Lake or Streambed Alteration Agreeemnt No. 1600-2015-0082-R5). This project is part of a larger project titled: "Li
Document Type
NOD - Notice of Determination
Received
Posted
9/18/2015
Present Land Use
State Highway, Transportation Corridor, Open Space, & Agriculture
Document Description
CDFW has executed Lake and Streambed Alteration Agreement no. 1600-2015-0082-R5, pursuant to section 1602 of the fish and game code to the project applicant, Craig Murray with the Carpinteria Sanitary District. The project entails re-routing an existing sewer main line, owned by the Carpinteria Sanitary District, approximately 120 ft north from its existing location to move it out of the way of the larger proposed Caltrans Linden Avenue and Casitas Pass Interchanges Project located in the same area. The new sewer main line will be installed using a horizontal directional drilling method. A frac-out plan has been developed and will be followed in the event of a frac-out. If there is water present at the time of construction, Carpinteria Creek will be dewatered using a cofferdam to avoid complications from a frac-out. If a water diversion becomes necessary, the project proposes to impact no more than 0.095 acre of riparian habitat within Carpinteria Creek to install and operate the diversion. Should this occur, a revegetation/restoration plan will be submitted and implemented upon CDFW approval.

Contact Information

Name
Sarah Rains
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Carpinteria
Counties
Santa Barbara
Cross Streets
Linden Avenue
State Highways
101
Waterways
Frnaklin Creek and Carpinteria Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.