Barren Ridge Renewable Transmission Project (Lake and Streambed Alteration Agreement No. 1600-2014-0235-R5)
24 Documents in Project
Summary
SCH Number
2008041038
Lead Agency
City of Los Angeles
Document Title
Barren Ridge Renewable Transmission Project (Lake and Streambed Alteration Agreement No. 1600-2014-0235-R5)
Document Type
NOD - Notice of Determination
Received
Posted
3/26/2018
Present Land Use
Multiple Land Uses
Document Description
Proposed project involves the construction of 61 miles of new 230 kV transmission line, and reconductoring 76 miles of existing 230 kV transmission line with larger-capacity conductors. The project will result in impacts to 17.35 acres of streambed including temporary impacts to 10.79 acres; the project will permanently remove 6.56 acres of streambed.
Contact Information
Name
Eric Weiss
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Cities
California City
Counties
Kern, Los Angeles
State Highways
Hwy 5, 14, 58, 210
Waterways
Santa Clara River
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes