McEvoy Ranch - Water Right Applications and Petitions for Change of Place of Use and Extension of Time

2 Documents in Project

Summary

SCH Number
2008032080
Lead Agency
State Water Resources Control Board
Document Title
McEvoy Ranch - Water Right Applications and Petitions for Change of Place of Use and Extension of Time
Document Type
NOD - Notice of Determination
Received
Posted
3/26/2009
Document Description
Approval of two water right Applications, five Petitions for Change of existing permitted and licensed water rights, and four Petitions for Extension of time for the McEvoy Ranch. The project consists of water diversion and storage for irrigation of approximately 153 acres of existing and proposed olive orchard. Water will be diverted from an Unnamed Stream tributary to San Antonio Creek, thence the Petaluma River. Other existing and proposed water uses include fire protection, stockwatering, and recreation. The project includes expansion of existing water storage reservoirs, establishing new olive orchards, and allowance of additional time to put water beneficial use under existing water right permits.

Contact Information

Name
Aaron Miller
Agency Name
State Water Resources Control Board, Division of Water Rights
Contact Types
Lead/Public Agency

Location

Cities
Petaluma
Counties
Marin
Cross Streets
Nearest major intersection is Petaluma-Point Reyes Road and Novato Boulevard
Zip
94952
Total Acres
550
Parcel #
125-070-05, 06, 16
Waterways
Unnamed Stream Tributary to San Antonio Creek
Township
7N
Range
4W
Section
30, 31
Base
MDB&M

Notice of Determination

Approving Agency
State Water Resources Conrol Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.