Document Description
Approval 30363 seeks a right to appropriate ten acre-feet per annum of water to storage behind an offstream pit-type reservoir at a rate not to exceed 0.5 cubic feet per second. Water will be diverted from Forsythe Creek to an existing offstream reservoir from December 15 to March 31. Water collected to storage pursuant to this application will be used for irrigation and frost protection of 25 acres. A pump installed at the point of diversion on Forsythe Creek will transport water to the reservoir via an existing 500-foot, four-inch diameter underground pipeline. A second pump installed at the reservoir will transport water for irrigation of the proposed place of use via an existing 50-foot-long, 12-inch-diameter pipeline. The reservoir has an approximate surface area of one acre when full.
Contact Information
Name
Luann Erickson
Agency Name
State Water Resources Control Board, Division of Water Rights
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Mendocino
Cross Streets
Uva Drive, North State Street, and U.S. Highway 101
Zip
95470
Total Acres
26
Parcel #
162-130-02, 06
State Highways
US 101
Waterways
Forsythe Creek tributary to West Fork Russian River
Township
16N
Range
12W
Section
6
Base
MDB&M
Other Location Info
City/Nearest Community: Redwood Valley
Notice of Determination
Approving Agency
State Water Resources Control Board
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes