Pittsburg Civic Tower and Davi Avenue Roadway Improvement Project

3 Documents in Project

Summary

SCH Number
2008032015
Lead Agency
City of Pittsburg
Document Title
Pittsburg Civic Tower and Davi Avenue Roadway Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
4/14/2008
Present Land Use
Zoning: Governmental/Quasi Public General Plan: Public/Institutional
Document Description
The proposed project includes approval of a Disposition and Development Agreement, minor subdivision and design review approval for construction of a 133,400 square foot, six-story mid-rise office building (Civic Tower), a 6,500 square foot restaurant and related parking and site improvements on an approximately eight-acre site. The subdivision would involve the creation of two small parcels measuring approximately 39,238 square feet and 11,966 square feet to accommodate the footprint and the surrounding pavement walkways of the Civic Tower and restaurant, respectively. The entire parking lot, the multi-use path and the perimeter landscaping would remain under the ownership of the City and a non-buildable easement would be placed around the two new parcels.

Contact Information

Name
Leigha Schmidt
Agency Name
City of Pittsburg Planning Dept.
Contact Types
Lead/Public Agency

Location

Cities
Pittsburg
Counties
Contra Costa
Cross Streets
Railroad Avenue and State Route 4
Zip
94565
Total Acres
~ 8
Parcel #
086-100-022, 024, 025, 026
State Highways
4
Railways
UPRR and AT&SF Railroads
Schools
Pittsburg High, Parkside, and Los Medanos
Waterways
Suisun Bay, Mokelumne Aqueduct, Kirker Creek, and Contra Costa Canal

Notice of Determination

Approving Agency
City of Pittsburg
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print