Construction of a New Water Storage Tank on Skyline Drive in the Ponderosa Hills Subdivision

2 Documents in Project

Summary

SCH Number
2008032001
Lead Agency
Tuolumne Utilities District
Document Title
Construction of a New Water Storage Tank on Skyline Drive in the Ponderosa Hills Subdivision
Document Type
NOD - Notice of Determination
Received
Posted
4/11/2008
Present Land Use
R-1:MX
Document Description
Proposing to construct a new water storage tank with 600,000 gallons of capacity, and related clearing, grading, and pipeline trenching. The proposed tank will be welded steel, painted to match the surroundings and will be 32 feet high and 58 feet in diameter. Approximately 336 cubic yards of soil will be cut and disposed of off-site. Trenching of approximately 130 linear feet will be required for pipeline installation. The tank is necessary to replace an existing 100,000 gallon tank which has deteriorated. The larger size is necessary to supplement needed storage of this water system.

Contact Information

Name
Kelly Stuart Klyn
Agency Name
Tuolumne Utilities District
Contact Types
Lead/Public Agency

Location

Counties
Tuolumne
Cross Streets
Skyline Drive and Ponderosa Way
Zip
95379
Total Acres
0.58 (parcel)
Parcel #
087-100-20
State Highways
108
Schools
Soulsbyville Elementary
Waterways
North Fork Tuolumne River, Turnback Creek, Curtis Creek
Township
2
Range
16
Section
29
Base
MDB&M
Other Location Info
City/Nearest Community: Tuolumne

Notice of Determination

Approving Agency
Tuolumne Utilities District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.