Storm Water Master Plan Implementation - Percolation Pond A8-1
Summary
- SCH Number
- 2008028143
- Public Agency
- California State University, Monterey Bay (CSUMB)
- Document Title
- Storm Water Master Plan Implementation - Percolation Pond A8-1
- Document Type
- NOE - Notice of Exemption
- Received
- Posted
- 2/20/2008
- Document Description
- This project will create pond A8-1, a 1.74-acre depression five feet deep, that will capture storm water runoff from approximately 60 acres of upstream asphalt. This pond is part of the implementation of the CSUMB Storm Water Master Plan (SWMP) which recommends percolation basins for each sub-watershed throughout the campus in order to meet the goal of retaining all sotrm water runoff onsite. Each basin is to be designed to retain/infiltrate the storm water runoff generated within the sub-watershed during a 100-year, 24-hour storm event, using some existing and proposed storm drain facilities.
- Contact Information
-
Tony Boles
California State University, Monterey Bay
Lead/Public Agency
100 Campus Center
Seaside, CA 93955
Phone : (831) 582-4766
Location
- Cities
- Seaside
- Counties
- Monterey
Notice of Exemption
- Exempt Status
- Categorical Exemption
- Type, Section or Code
- 15304 and 15061(b)(3)
- Reasons for Exemption
- Minor alteration to land.
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.