Deer Creek Road Paving, Water Line, and Crossing

3 Documents in Project

Summary

SCH Number
2008022134
Lead Agency
El Dorado Irrigation District
Document Title
Deer Creek Road Paving, Water Line, and Crossing
Document Type
NOD - Notice of Determination
Received
Posted
4/29/2008
Present Land Use
Agricultural and Rural Residential
Document Description
The project consists of improvements identified by the El Dorado County Fire Marshall and includes: (1) improving the existing crossing allowing two-way access and added flood capacity; (2) installation of approximately 6,020 feet of 8-inch diameter water line and appurtenances in Deer Creek Road to provide adequate fire protection flow to the DCWWTP, and fiber optic conduit; (3) install approximately five fire hydrants along Deer Creek Road; (4) widening approximately 4,860 linear feet of Deer Creek Road south of Flying "C" Road to provide adequate emergency access; and (5) grading, paving, culvert replacement, and other incidental improvements typically associated with road standards and maintenance required for safe use of the roadway.

Contact Information

Name
Dena McCann
Agency Name
El Dorado Irrigation District
Contact Types
Lead/Public Agency

Location

Counties
El Dorado
Cross Streets
Flying C Road - on Deer Creek Road, approximately 2.5 miles south of Cameron Park
Zip
95682
Total Acres
2.01
Parcel #
109-010-051, 071, 081, 101, 131, 141, 151
State Highways
50
Waterways
Deer Creek
Township
9N
Range
9E
Section
16
Base
MDB&M
Other Location Info
City/Nearest Community: Cameron Park

Notice of Determination

Approving Agency
El Dorado Irrigation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A