Power Generation Station Renewable Energy Expansion Project

2 Documents in Project

Summary

SCH Number
2008022120
Lead Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Power Generation Station Renewable Energy Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
4/11/2008
Present Land Use
Wastewater treatment plant
Document Description
The PGS Renewable Energy Expansion Project will increase power and heat generation capabilities of existing cogeneration facilities at the EBUD Main Wastewater Treatment Plant (MWWTP). This project will utilize excess biogas from the MWWTP that is currently flared and wasted due to capacity limitations. The proposed project will have the capacity to produce an additional nine megawatts of "green" energy for use on-site or sale to PG&E or a third party. Power production from this renewable resource would help reduce California's dependency on fossil fuels for energy production. As part of this project, EBMUD will modify its interconnection agreement with PG&E and may negotiate a sales agreement with a third party for revenue generation. The project will not require construction of new off-site infrastructure, such as new power lines, to facilitate this transfer of additional power. Construction of facilities necessary for the expanded power generation will be confined to within the boundaries of the existing MWWTP. Completion of construction is expected by early 2010.

Contact Information

Name
Vince De Lange
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
Wake Avenue and West Grand Avenue
Zip
94607
Total Acres
0.5
Parcel #
0305-002-03
State Highways
24, 80, 580, 880
Railways
UPRR, BNSF
Waterways
San Francisco Bay

Notice of Determination

Approving Agency
East Bay Municipal Utility District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print