Crystal Springs / San Andreas Transmission Upgrade Project
11 Documents in Project
Summary
SCH Number
2008022054
Lead Agency
City and County of San Francisco
Document Title
Crystal Springs / San Andreas Transmission Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
10/21/2010
Document Description
The Operator proposes to upgrade Upper and Lower Crystal Springs and San Andreas Reservoir infrastructure. Project upgrades include the following for one or all of the reservoirs: new outlet structures and dam culverts; pipeline repair and replacement; a new pump station with related facilities, valves, and piping; and pipeline access improvements. Specifically, the proposed Project would (1) improve the seismic reliability of the Crystal Springs/San Andreas Transmision System (CS/SA Transmission System) by reducing facility vulnerability to earthquake-related damage to improve the likelihood of its continued operation following a seismic event; (2) ensure that the CS/SA Transmission System provides transimission flexibility to the regional water system in a manner that will enable the SFPUC to meet its delivery reliablity goals in the event of an emergency or during major water system maintenance.
Contact Information
Name
Wes Stokes
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Burlingame, Hillsborough, Millbrae
Counties
San Mateo
Cross Streets
Skyline Blvd, I-280
Total Acres
135
Parcel #
093070998, 093070071, 093070072...
State Highways
280, 92
Schools
Meadows ES, Odyssey
Waterways
San Mateo Creek
Base
SanMateo
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.