Modified Crystal Springs San Andreas Transmission Upgrade Project

11 Documents in Project

Summary

SCH Number
2008022054
Lead Agency
City and County of San Francisco
Document Title
Modified Crystal Springs San Andreas Transmission Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
9/7/2010
Document Description
Seismic and functional upgrades to the Upper Crystal Springs Dam Culverts, including seismic strengthening of the Lower Culvert, which crosses the San Andreas Fault rupture zones. Seismic improvements to the Crystal Springs Outlet Structures 1 and 2, including removal of the seismically vulnerable aboveground portions of the towers, and construction of a small onshore control shed for remote valve operation. Major seismic upgrade of the Crystal Springs Pump Station (CS Pump Station), including construction of a new, seismically strengthened Pump Station, and replacement of all related facilities, pipelines, and pipeline connections. The upgrade would also include increasing the pump station booster capability to 120 million gallons per day to meet delivery reliability goals, and construction of a new dissipation structure for releases into San Mateo Creek to meet anticipated DSOD requirements. Seismic upgrades to the existing CS/SA Pipeline that conveys water from CS Pump Station to San Andreas Reservoir (~4.7 miles), including replacement of 2 segments of the pipeline, general pipeline improvements (i.e., corrosion protection, replacement of valves, etc.), and new access roads to ensure access to the pipeline for emergency and maintenance repairs. Seismic upgrade to the San Andreas Outlet Structures 2 and 3, including improvements at both the outlet towers and tunnel portals located at the Harry Tracy Water Treatment Plant. Implementation of habitat mitigation sites including, but not limited to, full implementation of the San Andreas and Adobe Gulch habitat improvements sites.

Contact Information

Name
Timothy Johnson
Agency Name
City and County of San Francisco Planning Department
Contact Types
Lead/Public Agency

Location

Cities
Burlingame, Hillsborough, Millbrae
Counties
San Mateo
Cross Streets
Skyline Blvd, I-280
Total Acres
135
Parcel #
093070998, 093070071, 093070072...
State Highways
280, 92
Schools
Meadows ES, Odyssey
Waterways
San Mateo Creek
Base
SanMateo

Notice of Determination

Approving Agency
San Francisco Public Utilities Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print