Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade
11 Documents in Project
Summary
SCH Number
2008022054
Lead Agency
City and County of San Francisco
Document Title
Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2011
Document Description
In connection with approval of the project identified above, the SFPUC required compensatory habitat mitigation to address biological resources impacts that would result from implementation of the projects. Three habitat compensation sites, known as Homestead Pond, San Andreas Reservoir Wetlands, and Adobe Gulch Grasslands which are located within S.F. Peninsula Watershed lands that are owned by the City and County of San Francisco but managed by the SFPUC, will provide mitigation for certain of these impacts: On September 13, 2011, the SFPUC adopted Resolution No. 11-0156, authorizing the General Manager of the SFPUC to negotiate and enter into Water System Improvement Program (WSIP) funded Contract No. WD-2641R, Habitat Reserve Program, Homestead pond, San Andreas Reservoir Wetlands, and Adobo Gulch Grasslands, and upon successful negotiations, approve the plans and specifications for these three habitat compensation sites and award the contract.
Contact Information
Name
Timothy Johnson
Agency Name
Department of Water Resources Division of Safety of Dams
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Burlingame, Hillsborough, Millbrae
Counties
San Mateo
Cross Streets
Skyline Blvd, I-280
Total Acres
135
Parcel #
093070998, 093070071, 093070072...
State Highways
280, 92
Schools
Meadows ES, Odyssey
Waterways
San Mateo Creek
Base
SanMateo
Notice of Determination
Approving Agency
DWR - Division of Safety Dams
Approving Agency Role
Responsible Agency
Determinations
(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.