Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade

11 Documents in Project

Summary

SCH Number
2008022054
Lead Agency
San Francisco, City and County of (City and County of San Francisco)
Document Title
Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2011

Document Description
In connection with approval of the project identified above, the SFPUC required compensatory habitat mitigation to address biological resources impacts that would result from implementation of the projects. Three habitat compensation sites, known as Homestead Pond, San Andreas Reservoir Wetlands, and Adobe Gulch Grasslands which are located within S.F. Peninsula Watershed lands that are owned by the City and County of San Francisco but managed by the SFPUC, will provide mitigation for certain of these impacts: On September 13, 2011, the SFPUC adopted Resolution No. 11-0156, authorizing the General Manager of the SFPUC to negotiate and enter into Water System Improvement Program (WSIP) funded Contract No. WD-2641R, Habitat Reserve Program, Homestead pond, San Andreas Reservoir Wetlands, and Adobo Gulch Grasslands, and upon successful negotiations, approve the plans and specifications for these three habitat compensation sites and award the contract.

Contact Information
Timothy Johnson
Department of Water Resources Division of Safety of Dams
2200 X Street, Suite 200 P.O. Box 942836
Sacramento, CA 94236-0001

Phone : (415) 575-9035

Location

Coordinates
37°33'10"N 122°23'9"W
Cities
Burlingame Hillsborough Millbrae
Counties
San Mateo
Cross Streets
Skyline Blvd, I-280
Total Acres
135
Parcel #
093070998, 093070071, 093070072...
State Highways
280, 92
Schools
Meadows ES, Odyssey
Waterways
San Mateo Creek
Base
SanMateo

Notice of Determination

Approving Agency
DWR - Division of Safety Dams
Approving Agency Role
Responsible Agency
Final Environmental Document Available at
N/A

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print