Old Waterman Canyon Road Bridge Replacement Construction Project (C.I.P. project # SS 07-14)

2 Documents in Project

Summary

SCH Number
2008021110
Lead Agency
City of San Bernardino
Document Title
Old Waterman Canyon Road Bridge Replacement Construction Project (C.I.P. project # SS 07-14)
Document Type
NOD - Notice of Determination
Received
Posted
6/26/2012
Present Land Use
Open Space - Watershed (OS/W)
Document Description
CDFG is executing a Lake or Streambed Alteration Agreement (SAA # 1600-20101-0277-R6 [Revision 1] pursuant to Section 1602 of the Fish and Game Code to the project Applicant: City of San Bernardino represented by Robert Eisenbeisz, 300 N. D Street, City of San Bernardino, State of California, 92418, Phone (909) 384-5203. The Old Waterman Canyon Road Bridge Rehabilitation Project is limited to the repair of existing girders and abutments of the Old Waterman Canyon Road Bridge, backfilling the void under the existing drop structure downstream of the bridge, and the installation of concrete rock slope protection along the north and south embankment downstream of the bridge.

Contact Information

Name
Kimberly Freeburn-Marquez
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
Cross Streets
Old Waterman Canyon Road, approximately 3/4 mile north of Waterman Avenue (Hwy 18)
Zip
92404
Total Acres
2.23
Parcel #
0270-061-11
State Highways
18
Township
1N
Range
4W
Section
11
Other Information
Lat./Long.: 34° 11' 29" N / 117° 16' 26" W

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes