Interim Renewal Contract Among The State of California Department of Water Resources, United States Bureau of Reclamation, and the Cross Valley Canal Contractor

8 Documents in Project

Summary

SCH Number
2008021074
Lead Agency
Water Resources, Department of (California Department of Water Resources)
Document Title
Interim Renewal Contract Among The State of California Department of Water Resources, United States Bureau of Reclamation, and the Cross Valley Canal Contractor
Document Type
NOD - Notice of Determination
Received
Posted
3/8/2018

Document Description
To provide interim water service conveyance for the Central Valley Project-Cross Valley Canal (CVP-CVC). The project will allow short-term use of California State Water Project (SWP) facilities to convey CVP water to the CVC contractors. In accordance with an approved water delivery schedule, federally contracted CVP-CVC water supplies will be conveyed from the Clifton Court Forebay at the Sacramento-San Joaquin Delta, through the SWP facilities, to the CVC turnout in Reach 12E of the California Aqueduct or to other points of diversion mutually agreed to in writing by DWR and the CVC contractor. The CVP-CVC water supplies may also be conveyed to the San Luis Reservoir as part of the federal share of storage for later release and delivery to the CVC contractor. A Negative Declaration for this project was certified in 2008. The term of this proposed agreement will be from March 1, 2018 through February 29, 2020.

Contact Information
Robert Cooke
California Department of Water Resources
State Water Project Analysis Office 1416 Ninth Street
Sacramento, CA 95814

Phone : (916) 653-8725

Location

Cities
Bakersfield Fresno Los Banos Tulare
Counties
Fresno Kern Merced Tulare
State Highways
I-5
Waterways
California Aqueduct, Kern River, Friant-Kern Canal

Notice of Determination

Approving Agency
California Department of Water Resources
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
1416 9th St., Room 1620, Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search