Summer 2008 Relocatables
2 Documents in Project
Summary
SCH Number
2008021040
Lead Agency
Moreno Valley Unified School District
Document Title
Summer 2008 Relocatables
Document Type
NOD - Notice of Determination
Received
Posted
4/17/2008
Present Land Use
Elementary School and Middle Schools
Zoning: P (Public Facilities)
General Plan: P (Public Facilities)
Document Description
The proposed project would consist of the placement and operation of relocatable classrooms at the four schools listed above. Nine relocatables would be placed at each of the three middle schools, and two relocatables at Edgemont Elementary School. The new classrooms would assist the Moreno Valley Unified School District in meeting their class size reduction goals at the four schools. The proposed project would not increase student enrollment or capacity at any of the schools.
Contact Information
Name
Sergio San Martin
Agency Name
Moreno Valley Unified School District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Moreno Valley
Counties
Riverside
Cross Streets
Eucalyptus Ave/Day St, Delphinium Ave/Indian St, Morrison St/Dracaea Ave, Eucalyptus Ave/Heacock
Zip
92553, 555
Parcel #
291440051, 482230018, 487370005, 487370006, 487390001, 487391001, 292140002
State Highways
SR-60, I-215
Railways
BNSF
Airports
March Air Reserve Base
Schools
Many
Waterways
Perris Valley Storm Drain, Quincy Channel
Township
3S
Range
4W, 5W
Section
1
Notice of Determination
Approving Agency
Moreno Valley Unified School District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.