Ultra Violet Treatment Facility

3 Documents in Project

Summary

SCH Number
2008012120
Lead Agency
City of Palo Alto
Document Title
Ultra Violet Treatment Facility
Document Type
NOD - Notice of Determination
Received
Posted
5/16/2008
Present Land Use
Existing Regional Water Quality Control Plant Zoning: Public Facility with Site & Design Overlay General Plan: Major Institution/Special Facility
Document Description
The proposed project would replace the Palo Alto Regional Water Quality Control Plant's (RWQCP) existing chlorine disinfection facility with an ultraviolet (UV) disinfection facility which would be built adjacent to the existing Chlorination Station building. The new UV facility would consist of a concrete channel structure approximately 80 feet long and 45 feet wide, sitting 11 feet above grade. The UV facility and the associated lamp washdown and cleaning area would be permanently covered by an unenclosed structure that would be approximately 30 feet tall. The project includes the installation of photo voltaic panels on the structure's roof top.

Contact Information

Name
Clare Campbell
Agency Name
City of Palo Alto
Contact Types
Lead/Public Agency

Location

Cities
Palo Alto
Counties
Santa Clara
Cross Streets
Embarcadero Way / Embarcadero Road (2501 Embarcadero Way)
Zip
94303
Parcel #
008-05-001, 005
State Highways
101
Airports
Palo Alto Airport
Waterways
San Francisco Bay

Notice of Determination

Approving Agency
City of Palo Alto
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No