City of Martinez Marina Maintenance Dredging Amendment 1 [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2017-029-03 (ITP) Amendment 1
5 Documents in Project
Summary
SCH Number
2008012065
Lead Agency
City of Martinez
Document Title
City of Martinez Marina Maintenance Dredging Amendment 1 [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2017-029-03 (ITP) Amendment 1
Document Type
NOD - Notice of Determination
Received
Posted
12/28/2017
Document Description
The proposed project includes hydraulic dredging a small portion of the Martinez Marina to a maximum depth of -9 feet MLLW with an additional 1 foot of over dredge allowance. The estimated maximum volume of dredged material per event is 50,000 cubic yards over a surface area of approx. 7.5 acres. It is likely that over the life this permit, two separate dredging events will occur totaling a maximum of 100,000 cubic yards of material being removed. Sediment will be removed using a cutterhead hydraulic suction dredge and with material being conveyed via an 8- to 12-inch diameter pipe to the City of Martinez upland disposal ponds located southeast of the marina.
This Amendment No. 1 will extend the work window from Nov. 30, 2017 to Dec. 15, 2017 only. This increase in the work window will not result in the increase in the volume of material dredged, but may expose covered species to potential take at the same rate as covered in the original ITP. The Amendment referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.
Contact Information
Name
Jim Starr
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Cities
Martinez
Counties
Contra Costa
Zip
94553
Total Acres
70
Parcel #
373-040-003
Waterways
Southern shore of Suisun Bay where it joins with the Carquinez Strait
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No