Valley-Ivyglen Subtransmission Lin

12 Documents in Project

Summary

SCH Number
2008011082
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Valley-Ivyglen Subtransmission Lin
Document Type
NOD - Notice of Determination
Received
Posted
8/28/2018
Present Land Use
various
Document Description
Construction of a new, single circuit 115 kV subtransmission line and fiber optic line. The route would be approximately 27-miles long and constructed within approximately 23 miles of new ROW. The line would traverse unincorporated Riverside County and the cities of Menifee, Perris, and Lake Elsinore. Installation of overhead fiber optic lines on the proposed structures and underground in new (approximately 10,000 ft) and existing (approximately 13,200 ft) conduit. Transfer of existing distribution circuits along portions of the proposed subtransmission line to new 115-kV structures or to underground positions. Installation of new 115 kV switching and protective equipment at both Valley and Ivyglen Substations.

Contact Information

Name
Jensen Uchida
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Lake Elsinore, Perris
Counties
Riverside
Cross Streets
State Hwy 74 E & Menifee Rd (Valley Substation), Temescal Canyon Rd & Maitri Rd. (Ivyglen Sub.)
Zip
92530
Total Acres
280
Parcel #
Multiple
State Highways
Hwy 74, 15, 215
Railways
BNSF
Airports
Perris Valley, Skylark
Schools
Several
Waterways
Lake Elsinore, San Jacinto River, Canyon River, Corona Lake, Canyon Lake

Notice of Determination

Approving Agency
CA Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print