San Andreas Sanitary District Digester Upgrade Project

11 Documents in Project

Summary

SCH Number
2007122100
Lead Agency
San Andreas Sanitary District
Document Title
San Andreas Sanitary District Digester Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
11/7/2014
Present Land Use
Public Service
Document Description
The Project proposes to upgrade the existing anaerobic digester at the San Andreas Sanitary District's (SASD) wastewater treatment plant (WWTP). The project is designed in accordance with and is supplemental to the SASD Facilities Master Plan. The existing digester will be upgraded and continue to treat primary sludge and a separate aerobic digester will be constructed to treat waste activated sludge. A density meter will be added to the primary sludge discharge header to ensure feeding thick primary sludge to the anaerobic digester. Construction will last approximately one year and is tentatively planned from spring of 2015 to spring of 2016.

Contact Information

Name
Meagan O'Deegan
Agency Name
San Andreas Sanitary District
Contact Types
Lead/Public Agency

Location

Counties
Calaveras
Cross Streets
Gold Strike Road and Gold Oak Road
Zip
95249
Total Acres
6
Parcel #
40012039
State Highways
Hwy 49, 12, 88
Schools
Calaveras HS
Waterways
Murray Creek
Township
4N
Range
11E
Section
13
Base
MDB&M
Other Location Info
City/Nearest Community: San Andreas

Notice of Determination

Approving Agency
San Andreas Sanitary District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes